Public capacity leaderboard · July 2026

30 companies shaping
the AI infrastructure race.

One major campus per operator or consortium, ranked by its largest comparable public power figure—not by total worldwide fleet size.

25.03 GWcombined reported scale
30operators or consortia
13countries represented
Largest MW first1 GW = 1,000 MW Operational Building / mixed Announced
How to read this listOperational, building, and announced projects appear together because operators rarely publish live facility IT load. Campus envelope, electrical capacity, and critical IT load are not identical; each row labels its measurement basis.
01

Meta

Building

Hyperion

Richland Parish, Louisiana, United States
5 GWMaximum campus envelope

Designed to scale toward 5 GW. This is the maximum planned cluster scale, not today’s energized IT load.

02

Amazon Web Services

Operational + expanding

Project Rainier

Northern Indiana, United States
2.2 GWMulti-building campus

The full campus figure includes the active Trainium AI cluster and continued expansion; AWS does not publish a separate live IT-load figure.

03

Microsoft

Announced

Pecos AI Campus

Pecos, Texas, United States
~2 GWPlanned capacity addition

Microsoft says roughly 2 GW will be delivered over five to seven years, so the ranking uses the final planned scale.

04

Tract

Announced

Silver Springs Campus

Lyon County, Nevada, United States
Up to 1.6 GWMaximum site support

The site can support up to 1.6 GW. Its initial 700 MW remains subject to phased utility studies and tenant delivery.

05

DataVolt

Development

Oxagon AI Factory

Oxagon, NEOM, Saudi Arabia
1.5 GWFull project target

The first investment phase is one part of a 1.5 GW renewable-powered AI factory planned to enter service from 2028.

06

Vantage Data Centers

Announced

Frontier

Shackelford County, Texas, United States
1.4 GWCritical IT load

The full-build plan spans ten data centers engineered for dense, liquid-cooled AI deployments.

07

Nscale

Announced

Monarch AI Campus

Mason County, West Virginia, United States
Up to 1.35 GWCompute letter of intent

The up-to figure comes from a Microsoft Vera Rubin compute letter of intent, not currently energized capacity.

08

OpenAI · G42

Building

Stargate UAE

Abu Dhabi, United Arab Emirates
1 GWDedicated Stargate cluster

The dedicated cluster starts with a 200 MW phase inside the wider 5 GW UAE–US AI campus.

09

Google · AdaniConneX

Announced

Visakhapatnam AI Hub

Andhra Pradesh, India
Gigawatt-scale*Official scale description* sorting proxy

Google says “gigawatt-scale” but gives no exact MW. A 1,000 MW proxy is used only to place the project in this ranking.

10

Reliance Industries

Building

Jamnagar AI Campus

Jamnagar, Gujarat, India
Gigawatt-scale*Long-range program direction* sorting proxy

Reliance describes the wider campus program as gigawatt-scale. The separately contracted first Meta facility is 168 MW.

11

DATA4

Announced

Escaudain AI Campus

Hauts-de-France, France
700 MWFull-campus electrical capacity

A future cloud and AI campus whose published figure represents the completed site rather than an operating hall.

12

NEXTDC

Planned

S7 Sydney

Eastern Creek, Sydney, Australia
550+ MWPlanned IT capacity

NEXTDC markets S7 as a 550+ MW AI-ready campus; delivery remains subject to approvals and phased construction.

13

Aligned Data Centers

Building

Project Caprock

Hale County, Texas, United States
540 MWSix-facility campus

Published campus capacity across six cloud and AI-ready facilities, not one data hall.

14

YTL Power

Operational + building

YTL Green Data Center Park

Kulai, Johor, Malaysia
500 MWEntire park capacity

The operational NVIDIA AI deployment occupies only part of the wider renewable-powered data center park.

15

atNorth

Planned

DEN02 Varde

Varde, Denmark
500 MWFull campus power

The 500 MW campus begins with an initial 250 MW development phase.

16

Khazna · Eni

Announced

Ferrera Erbognone AI Campus

Lombardy, Italy
500 MWPlanned IT capacity

The figure is covered by heads of terms; final partnership terms and phase delivery still matter.

17

DataBank

Building

Red Oak Campus

Red Oak, Texas, United States
480 MWFull-build critical IT

The final campus is planned for 480 MW; its first construction phase accounts for 240 MW.

18

Applied Digital

Operational + building

Polaris Forge 1

Ellendale, North Dakota, United States
400 MWCritical IT load

The company filing reports 100 MW energized with the remaining campus capacity under construction in 2026.

19

ST Telemedia GDC

Operational + building

STT Jakarta Campus

Cikarang, Greater Jakarta, Indonesia
360+ MWMulti-building pipeline

The long-range IT-capacity pipeline spans several buildings and delivery phases rather than one live hall.

20

Compass Datacenters

Building

DFW Red Oak

Red Oak, Texas, United States
360 MWCampus development capacity

The operator publishes campus scale; tenant-specific AI load remains undisclosed.

21

AirTrunk

Operational

SYD3

Western Sydney, Australia
320+ MWWhole campus capacity

The live hyperscale campus supports high-density AI deployments but is not used exclusively for AI.

22

CoreWeave

Building

Lancaster AI Data Center

Lancaster, Pennsylvania, United States
Up to 300 MWExpansion potential

The initial committed facility is 100 MW, with expansion potential taking the site toward 300 MW.

23

Prime Data Centers

Operational + building

Chicago ORD01 Campus

Elk Grove Village, Illinois, United States
270 MWThree-building critical IT

The published total covers three AI-ready buildings at different delivery stages.

24

NTT DATA

Operational + building

Phoenix Campus

Mesa, Arizona, United States
240 MWFull-campus critical IT

The figure covers the entire expanding campus; each individual operational building is smaller.

25

STACK Infrastructure

Building

Johor Bahru Campus

Iskandar Puteri, Johor, Malaysia
220 MWTwo-building campus

A hyperscale campus designed for cloud and AI/ML workloads, with capacity delivered in phases.

26

EdgeConneX

Building

Greater Osaka Campus

Osaka, Japan
200 MWCampus electrical capacity

The AI-ready campus is under construction, with its first phase expected to enter service in 2028.

27

DC BLOX

Building

Atlanta West

Douglasville, Georgia, United States
200 MWPlanned critical load

A purpose-built AI-ready hyperscale campus whose published capacity represents full development.

28

Digital Realty

Building

Dugny Digital Hub

Dugny, Paris, France
176 MWThree data centers

The total IT capacity spans three AI-ready facilities; the first delivery is planned for 2027.

29

CyrusOne

Announced

LON6

Iver Heath, Buckinghamshire, United Kingdom
90 MWPlanned IT load

A planned London-region facility; the figure is not current operating load.

30

Pure DC

Building

Amsterdam Westpoort AMS01

Amsterdam, Netherlands
78 MWHigh-density campus

The substation is live while the data halls remain under phased construction.

Not a definitive global ownership ranking

Public disclosures change quickly and often mix future campus envelopes with operational load. Google and Reliance use “gigawatt-scale” wording, so 1,000 MW is only a sorting proxy. xAI, HUMAIN, Baidu, Alibaba Cloud, and Switch are not force-ranked where a comparable official single-campus MW figure could not be verified.

NEXT ROUTE

Now see what those megawatts power.

Explore a living Three.js model of the grid, UPS, GPU racks, fiber network, and liquid-cooling loop.